Project’s Key Dates

2016 September – 2017 August

ZAC reference book – Additional impact study – Water law file act – Demolition permit – Building permissions & private land negotiations.

2017 September – November

Asbestos removal work – public buildings demolition.

2018 May – 2019 November

Phase 1: «L’AVAL» (downstream) construction starts, works to include public infrastructure (bus station, nursery & new tourism office).

2019 May – 2020 November

Phase 2: «Central» construction starts

2021 May – 2022 November

Phase 3: « L’AMONT » (Upstream) construction, including the underground APM.

Respect for this schedule will depend on land negotiations and the lack of recourse against buil-ding permits.

L’Aval

The first phase of the project will include the new Val d’Isère tourism office, bus station, nursery, a 50 room hotel & 20 apartments, designated as hotel residences.

Le Centre

The second phase of Le Coin de Val, will see the relocation of existing businesses and the creation of new ones, as well as apartments and a new hotel, the «Val Tower».

L’Amont

The third phase will see the relocation of existing businesses as well as the creation of new ones and the building of apartments. It will also include the construction of the underground APM.

Val d’Isère : 1950-2030

Le Coin de Val